Project Description

Project History

The project was authorised in the summer of 2012 and entered the phase of construction in the summer of 2012. The company concluded a contract with LAGIE SA for the project in January 2012, with a price Feed in Tariff: 0.404 €/kWh. The station was connected to the network of DEDDIE SA in February 2012 and thereafter works seamlessly.

Position: “Paliodragatsa” of the Municipal Unity Prosilio, Municipality of Amfissa, Prefecture of Fokida
Power: 99,875kWp
Ownership: Energy Trading SA
Project Phase: In operation
Technology: Photovoltaic
Equipment: Panel: Conergy ECOPRO 235P, 8 x Kaco Powador 14.0 TL, 8 x Tracking System Technometalliki MEPE