Project Description
The project was authorised in the summer of 2012 and entered the phase of construction in February 2013. The company concluded a contract with LAGIE SA for the project in January 2012 ,with a price Feed in Tariff: 0.404 €/kWh. The station was connected to the network of DEDDIE SA in March 2013 and thereafter works seamlessly.
| Position: |
“Soulianata” of the Municipal Unity Mousata, Municipality of Argostoli, Prefecture of Kefalonia. |
| Power: |
99,9kWp |
| Ownership: |
NL Wallamsters LTD |
| Project Phase: |
In operation |
| Technology: |
Photovoltaic |
| Equipment: |
Panel: Conergy 240PX, Inverter: 2X Power One Aurora 25, 2x Power One Aurora 20, Galvanised Steel by ELVAN ABEE |
| Production Data: |
289.000 kWh until October of 2013 |